UAV 2012 vs. UAV-GC 2005: which conditions suit your construction project?

Construction contracts in the Netherlands almost always refer to standard terms and conditions. The two most widely used sets are the UAV 2012 (Uniform Administrative Conditions for the execution of works and technical installation works 2012) and the UAV-GC 2005 (Uniform Administrative Conditions for Integrated Contracts 2005). But what are the main differences, and which conditions best suit your project?

Traditional contracting: UAV 2012

The UAV 2012 were developed for the traditional form of construction organisation. The client is responsible for the design and engages a contractor to carry out the work. The main characteristics:

  • A clear separation between design (client) and execution (contractor)
  • Site supervision by or on behalf of the client
  • Risk allocation in which design errors are at the client’s expense
  • Dispute resolution through the Arbitration Board for the Construction Industry (Raad van Arbitrage voor de Bouw)

The UAV 2012 provide a balanced allocation of rights and obligations and are suitable for projects in which the client wants to keep control of the design.

Integrated contracts: UAV-GC 2005

The UAV-GC 2005 were developed for integrated contract forms such as Design & Build, Design & Construct and turnkey projects. The contractor is responsible for both design and execution:

  • Combined responsibility for design and execution with the contractor
  • Functional specifications from the client instead of detailed specifications
  • More design freedom for the contractor
  • Adjusted risk allocation in which more risks lie with the contractor

The main differences at a glance

AspectUAV 2012UAV-GC 2005
Design responsibilityClientContractor
Type of specificationDetailed specificationFunctional requirements
Site supervisionYesNo (review afterwards)
Additional workDetailed arrangementMore limited arrangement
Risk allocationMore with the clientMore with the contractor

Which conditions should you choose?

The choice between the UAV 2012 and the UAV-GC 2005 depends on several factors:

Choose the UAV 2012 when:

  • As the client, you want control over the design
  • The project has a detailed specification
  • You want to supervise the work during execution
  • The project is relatively simple or standard

Choose the UAV-GC 2005 when:

  • You want to make the contractor responsible for both design and execution
  • You work with functional specifications
  • The project requires innovative solutions
  • You want a single point of contact for the entire project

Need advice?

The choice of conditions has major consequences for the allocation of risk and for cooperation during the construction project. It is therefore wise to obtain legal advice in advance.

Thole Law B.V. has extensive experience in advising on and drafting construction contracts under both the UAV 2012 and the UAV-GC 2005. Feel free to contact us for a no-obligation conversation about your project.


Do you have questions about this topic? Contact Thole Law B.V. at info@thole-law.nl or call +31 (0)20 238 6315.